Construction Plans for 2025 Announced. 

Truestream construction plans for 2025 include 28 areas within the Kalkaska, Waters, Hart, and Scottville service districts, offering access to Truestream high-speed fiber internet for over 9,000 GLE members.

Registration will open in phases.

To view our dynamic map and determine your Truestream area, please enter your service address on the map found on the Availability & Status Map page.

Map of the Waters service area
Phase 1: Kalkaska Build Sequence:
  • Mancelona 4
  • Mancelona 1
  • Clam River 2
  • Clam River 1
  • Clam River 3

Mainline construction is expected to be completed and lit in the spring of 2025, with construction to the home and in-home installations starting in the summer and continuing for several months.

Registration is open.

Register by Dec. 6 and return the paperwork by Dec. 20 to qualify for free in-home installation and to get on the construction list.

Phase 2: Kalkaska Build Sequence:
  • Westwood 3
  • Westwood 1 (partial)
  • Westwood 2
  • Kalkaska 2
  • Kalkaska 3
  • South Boardman 1
  • South Boardman 3
  • Fife Lake 1
  • South Boardman 2

Mainline construction is expected to be completed and lit in the summer of 2025, with construction to the home and in-home installations starting in the fall and continuing for several months.

Registration will open in January.

Map of the Waters service area
Image of the Waters and partial Kalkaska service district.
Phase 3: Waters and Hart Build Sequence:
  • Lovells 3 (permit pending area)
  • Lovells 4 (permit pending area)
  • Lovells 2 (permit pending area)
  • Weare 3
  • Weare 4
  • Weare 1

Mainline construction is expected to be completed and lit in the fall of 2025, with construction to the home and in-home installations starting in the winter of 2026 and continuing for several months.

Registration will open in April.

Phase 4: Scottville Build Sequence:
  • Riverton 4
  • Riverton 2
  • Riverton 1
  • Scottville 2
  • Scottville 1
  • Scottville 3
  • Scottville 4
  • Eden 3

Mainline construction is expected to be completed and lit in the winter of 2026, with construction to the home and in-home installations starting in the spring of 2026 and continuing for several months.

Registration will open July.

Map of the Waters service area

As construction continues throughout the year, additional details will be updated in our monthly construction updates at: https://www.truestreamfiber.com/news/.